“Box-in-box” method for renewal of modular joints

Principle

The mageba “box-in-box” method enables modular expansion joints to be replaced without any impact on the bridge’s structure. The substructure of the existing expansion joint is left in place, and a new joint is installed on top of it, with the support bar boxes of the new joint designed to fit into those of the existing one.

Applications

The “box-in-box” method is especially suitable when modular expansion joints are to be replaced with minimum impact on the bridge structure and in the quickest possible time.

Produktbroschüre Kasten in KastenProduktbroschüre Kasten in Kasten

Image gallery

  • Kasten-in-Kasten-img1

    Old 3-gap expansion joint after removal of asphalt and waterproofing membrane at each side

  • Kasten-in-Kasten-img2

    Cutting to enable the support bars of the old joint to be lifted out

  • Kasten-in-Kasten-img3

    Substructure after cleaning

  • Kasten-in-Kasten-img4

    New expansion joint during installation, after connection to the structure

  • Kasten-in-Kasten-img5

    Renewal of a 2-gap modular joint almost completed

  • Kasten-in-Kasten-img6

    Traffic management during renewal of a joint in phases